Today Enbridge finally came and disconnected my natural gas supply line and removed the meter. This is a very long process indeed. If I had to do this all over again, I need to call utility companies much earlier to get disconnection going.
Enbridge sent me a contract on September 18th informing me that the cost to cut off natural gas at main is $1300 + tax. I signed it and sent back to them on the same day. So today after 16 days, the natural gas is finally disconnected. Now Enbridge has indicated that it may take up to 44 days from the time request is received to the date work is completed. So I guess 16 days is a pretty good. But consider that I initiated the disconnection procedure on September 2nd, it took 32 days or just over a month to get natural gas disconnected. But looking at the brighter side, my house is finally ready for demolition.