Day 8 of EIFS installation. Today the base coat is being applied to the now flat and smooth surface. They put a fiberglass mesh on the surface and apply Flexcrete to create that cementitious surface. This is the south-east corner.
This is the north-east corner. The one that has foam board butt-joints with Roxul board clad non-combustible wall.
For this angle, you can see the meshes embedded in the Flexcrete surface.
At the end of the day, more than 50% of the house is coated with a base coat. Here’s the front of the house. The second floor still needs to be worked on.
Back of the house. Upper part of the south side still missing.
And here’s the 3rd floor.