Truck crew is back from Great Northern Insulation on Jan 20 to complete the rest of the missing areas.
Here the area under the balcony is sprayed.
The north side under the balcony, spray foam is also applied.
This joist space area is finally addressed with the entire space filled with spray foam.
The next day, the production supervisor came over and fixed up the last area where spray foam is not applied.
Now, spray foam work is finally completed. The next step is to put in all the batt insulation.