Framing for the basemen sliding doors

The basement will have some really big sliding doors installed. And we discovered some issue so that we had to frame a few areas so that the sliding doors can be installed properly. Here in front of the duct, we had to frame another set of walls in front for the sliding doors to come to the right distance from the wall.

Framing

Continue reading ‘Framing for the basemen sliding doors’ »

Vapour barrier day 2

Finishing up the vapour barriers. Here on the first floor the bottom sections are all completed.

Vapour barrier

Continue reading ‘Vapour barrier day 2’ »

Cedar day 3

The cedar siding is now finally finished toda

Cedar

Continue reading ‘Cedar day 3’ »

Strapping day 5

More strapping on the wall. For the north wall, we put the vapour barrier behind the strapping so that there are less chances that the vapour got punctured. This way when you hung a wall or otherwise make a hole on the wall, you are not going to make a hole on the vapour barrier as well.

Strapping

Continue reading ‘Strapping day 5’ »

Strapping day 4

We are doing more strapping today. First we had to remove the strapping on the south wall at the entrance area. We had to add another 1/2″ to it since it has to be strapped out 2″ rather than 1.5″. So we removed the existing ones and added a layer of 1/2″ plywood behind the wood and screw the strapping back on.

Strapping

Continue reading ‘Strapping day 4’ »

Strapping day 3

Doing more strapping work myself. Here on the west side of the house, the wall will not be used for anything so it is fully strapped horizontally.

Strapping

Continue reading ‘Strapping day 3’ »

Strapping day 2

Tried to do some strapping work by myself. Here on the 2nd floor in the bedroom, the walls are strapped horizontally. The left part of the bedroom here is going to be filled by a wall to wall closet. So certainly we are not going to need to find those vertical studs.

Strapping

Continue reading ‘Strapping day 2’ »

Strapping

Today we started strapping the inside of the exterior wall. As mentioned on the “Exterior wall construction with Swedish roots“, the exterior wall of this house is designed so that there is a 2×2 strapping on both the outside and inside of the 2×6 stud wall.

We started with the east side of the house. Instead of using 2×2 for strapping, we split the 2×4 in the middle and use the two pieces. We then pre-drill and then secure the strapping with 8×3 construction screws.

Strapping

Continue reading ‘Strapping’ »

Duct and fire rated assembly

The building inspector has indicated that Type-X drywall must be installed behind all metal duct works. So today we removed some of the existing duct works and installed 5/8″ Type-X drywall behind the ducts.

This is the first floor, from the left, you see Type-X drywall behind one furnace supply duct, three return air ducts, and two HRV supply/return duct. We’ve sealed any opening with fire block foam.

Fire rated wall assembly

Continue reading ‘Duct and fire rated assembly’ »

Header in a fire rated assembly

The north wall has to be fire rated. Here in Toronto, the requirement for header in a fire rated assembly can be satisfied by having 5/8″ Type-X drywall installed next to the rim board. The 5/8″ Type-X drywall provides 40 minutes of fire-resistance ratings. Add the rim board and the plywood and we will get the required 45 minutes fire-resistance rating that’s required.

Fire rated wall  Fire rated wall