Today the footings are being formed, inspected, and poured. The concrete work is done by Lee Rocca Forming Ltd out of Oakville.
The crew started the work late around 11:15AM because in typical Toronto style they are stuck in traffic on the QEW. I’ve scheduled the inspection with the inspector for 2pm and I wasn’t sure if they can make it on time. But the 5 men crew is very efficient, by 1:30pm, the form is done, and rebars are all placed.